Penfield Asbestos Repository

Project precis
Capping of former asbestos landfill covering over 10ha; placement of 20,000 m3 of fill. The site is subject to future redevelopment for open space or recreational use.

Click here to see survey of finished surface levels.

Project role
Principal Environmental Consultant and Contract Superintendent

Site investigations:

  • Investigations of extent of fill and natural materials using strict occupational health and safety protocols
  • Determination of extent of waste materials using strict occupational health and safety protocols

Remediation planning:

  • Preparation of contract documentation and technical specification for capping works, environmental management plan
  • Negotiations with contractor on scope of work and costs

Remediation implementation:

  • Supervision of works
  • Contract administration and superintendence using AS2124 as conditions of contract
  • Collection and analysis of validation samples
  • QA/QC method selection and assessment
  • Assessment and reporting of remediation works
  • Preparation of post capping site management plan

Client
Land Management Corporation

Project value
Approximately  $1million

Feature Projects

Brompton Redevelopment (Site 9) [read more]

Brompton Redevelopment (Sites 10 to 19) [read more]

Central West Precinct [read more]

Penfield Asbestos Repository [read more]

Womad Particulate Monitoring [read more]

Port Waterfront Particulate Monitoring [read more]

Adelaide Oval Redevelopment [read more]